PO confirmation not sent to ECC

November 30 0
Advertisement
Hi SNC Gurus
I have typical problem in PO collaboration, for PO confirmation. The PO is confirmed and published in SNC and showing status published, but the confirmation not updated on ECC side.
In application log (Transaction SLG1 - getting error as- PO XXX Item XXX: "ShippingPeriodEndDateTime should come before ShippingPeriodStartDateTime"
One more thing I checked is when PO delivry date is as per "Planned delivery date" in the material master then PO confirmation is working fine.
But when PO delivery date is not as per planned delivery time . ie suppose planned delivery time is 15 days in matl master but i enter delivery date in PO as equal to future 10 days then PO confirmation is not flowing from SNC to ECC..
Also please let me know how mode of transport duration in transportation lane affects PO shipping date on SNC side?
Will appriciate you early reply.
Thanks
VSK
Advertisement
Hi Nikhil
Thanks for the reply, but in POC3 we have only below validation profiles maintained
POC3     PO_COMPONENT_PRODUCT_INVALID     A Active
POC3     PO_COMPONENT_PRODUCT_MISSING     A Active
POC3     PO_COMPONENT_QUANTITY_MISSING     A Active
POC3     PO_COMPONENT_UOM_INVALID     A Active
POC3     PO_COMPONENT_UOM_MISSING     A Active
The profile you mentioned is not maintained.
Thanks
VSK
PO confirmation not sent to ECC

Hi SNC Gurus I have typical problem in PO collaboration, for PO confirmation. The PO is confirmed and published in SNC and showing status published, but the confirmation not updated on ECC side. In application log (Transaction SLG1 - getting error as

Update Process Order Confirmations Back to SAP ECC

Hi, Is there a document or step by step guide which explains how i can update  SAP EARP with process order confirmations from my shopfloor?  Below is the scenario i am looking for help in 1. There is a SQL server table where the SHOP floor update the

Transfer of Z field of Confirmation of Goods to ECC

Hello Experts, We are implementing Classic scenario of Self Service Procurement. In confirmation of goods we have created a Zfield at Item level. Which is a standard field in R/3 MIGO. We want to transfer this field in R/3 MIGO. How can we do it? Ple

Central Contract Mngt: Contract Confirmation Out not triggering from ECC

Hi, Can some one take a look at this and let me know if you have any suggestions After following note 1268821 we have Contracts replicating from SRM to ECC via PI. However we are not getting the Contract Replication Confirmation Out triggering from E

SUS ASN/POR without using confirmation key in ECC

hi gurus, would like to verify if to use SUS ASN or POR without having confirmation key in ECC is possible? we are on MM-SUS scenario (ECC6 & SRM7). thanks, ggHi ASN is controlled thorugh Confirmation Control Key in ECC PO. For POR you dont need this

SA Confirmations to ECC

We are trying to bring in SA Confirmations from SNC to ECC. I did implement the OSS note related to EDI messages and using ORDRSP.ORDERS05 for this. I would appreciate if anyone could provide information on how the idocs were mapped in PI or any tips

How to find out Shopping Cart created in backend system or ECC system

Hi All, I am new  to SAP SRM7.0.  The Client has implemented "Extended Classic Scenario".  i.e. SC>Approval>PO>Confirmation>Invoice process in ECC. We created few SC with "Free text" i.e. Describe what you need option in SC

CLEAN_REQREQ_UP not updating the status of all confirmations.

Hello All We have scheduled the cleaner report as a job running every 2 minutes. This job changes the status of the confirmations from 'Approved' to 'Transmit to backend system'. However the job doesn't process a few confirmations randomly. In such c

XI to ECC connection issue.

Hi.. I am doing MM-SUS Interface. I am getting the PO Confirmation from SUS-XI-ECC. when getting the PO confirmationm, from XI to ECC connection is not available for some time .  After getting the Connection from XI to ECC , the PO Confirmation it wi

Best practice for confirmation creation?

Dear Experts, I would like to have your opinion on best practices for confirmation creation in classic scenario. Whether most organizations  prefer to create confirmation in SRM or ECC? One advantage of confirmation creation in SRM is that you can av

Schedule line appears twice for PO confirmation category in MD04

Dear All, In PO we have two confirmation category AB and LA. When I see in MD04 there are two schedule line as shipping notification of LA as well as for AB. From my analysis I found that it is appearing if the AB sequence is higher then the LA seque

IDOC extensions during Upgrade from Ver 4.6 to ECC 6.0

We are working on an Upgrade project wherein we are going from Ver. 4.6 to ECC 6.0. Can you guide us what all we need to do with the IDOC extensions alerady implimented in ver 4.6 in order to confirm them good with ECC 6. Also to be noted, we are mak

Approval of confirmation

Hi experts; We are using SRM 7, classic scenario. We activated one-level approval for confirmation. The SC requester was absent and his manager created the confirmation. The system should send the approval confirmation to the manager but since he him

Alert 7055 - Manual Approval Required, XML messages to ECC not Triggered.

Hi All, I have a behavior in our Client Production System. We have setup a process in which if a PO confirmation Dates are -5 / + 5 days appart then that line item should result in Manual Approval Required. Even though a PO line item is in Status  "M

Ecc 6 Version

Hi Sap Gurus Could anybody confirm me whether in Ecc 6 version B/W,CRM and SCM are inbuilt  or not and any other new components attached to the version. Full point will be rewarded for proper informationHi Siddarth, As far as my knowledge is concerne

My Power Mac G4 Cube support ECC SDRAM...Weird ?!?!

Actually, I've accidentally plug in one 512mb 133 ECC SDRAM(mixed with 2 normal SDRAM) into my G4 Cube and turn it on. When I checked the System Profiler, I realized something weird, I then turn it off asap and check the RAM again because I worry som

Idoc not showing in R/3

Hi, Iam Currentl running File to Idoc interface. Message is success in moni also and runtime workbecnh also. But when iam checking R/3 using WE19 tcode by giving date its not showing . It showing like no values found. Can anybody tel me what is the r

BAPI for Production Order creation ?

Hi Experts, I am new to PP module and as per my requirement I have to: 1. Create Production order in ECC 6.0     After searching BAPI explorer, SDN and other sites I could see that there is no BAPI for Create Production order.     In one of the link

Offline shopfloor requirement

Hi Folks, I have a requirement which encompasses implementing a solution for online and offline scenario. Contract Manufactures have to be provided with an ability to confirm POs from the shopfloor. The boundary conditions of the requirements are as

IDOC - Proxy Scenario.

Hi.. I am doing MM-SUS Interface. i am thinking the Adapters are IDOC-->Proxy, If my understanding is wrong, pls correct me. Today at 9 am i am sending the PO Request from ECC -XI-SUS , i am getting the PO Confirmation from SUS-XI-ECC after 2 days. t